Key numbers:4 years / 8,000 hours journey-level experience required. Must pass 2 exams: Law & Business + Electrical Trade. Passing score: 70%. Contractor bond: $25,000. License renewal: every 2 years. TRAP: 4,000 hours (2 years) is a common wrong answer. It's 4 YEARS = 8,000 hours.
B&P 7159Home Improvement Contracts
Contracts over $500 must be written and signed. Max down payment: 10% or $1,000 (whichever is LESS). Subcontractor payment: within 10 days of GC receiving payment. Preliminary 20-day notice: within 20 days to preserve lien rights. TRAP: 25% down payment is a common wrong answer. Exceeding 10%/$1,000 is a misdemeanor.
NEC Foundations (Art. 90, 100)
Art. 90.2NEC Scope
NEC covers buildings, structures, and premises wiring. Excludes: utility supply systems (generation, transmission, distribution). Utilities follow NESC, not NEC. TRAP: The NEC does NOT apply to utility company distribution systems.
Art. 100Key Definitions
Ampacity = current a conductor can carry continuously without exceeding temp rating. Branch Circuit = from final OCPD to outlets. Feeder = from service equipment to final branch-circuit OCPD. Grounded conductor = neutral (intentionally grounded). Grounding conductor (EGC) = green/bare wire to ground system. Dwelling Unit = must have living, sleeping, cooking, AND sanitation. TRAP: Mixing up "grounded" (neutral) and "grounding" (EGC) is the #1 definitions trap.
Branch Circuits (Art. 210)
210.8(A)GFCI Protection — Dwellings
GFCI required for all 125V, 15A/20A receptacles in: bathrooms (ALL receptacles, not just near sink), kitchens, outdoors (all heights), unfinished basements, garages, crawl spaces, laundry areas, boathouses, bathtub/shower areas. TRAP: "Within 6 feet of sink" is the OLD rule. Current NEC requires GFCI for ALL bathroom receptacles.
210.12(A)AFCI Protection
AFCI required for ALL120V, 15A/20A branch circuits throughout the dwelling unit. TRAP: "Bedrooms only" is the OLD rule. Current NEC requires AFCI for all 120V circuits in dwellings.
210.52Receptacle Spacing
Wall receptacles: no point more than 6 feet from a receptacle (12 ft max between receptacles). Kitchen countertop: no point more than 24 inches from a receptacle. Min 2 small appliance circuits (20A) required for kitchen. Garage: at least 1 receptacle (attached or detached). TRAP: Countertop spacing (24") is different from wall spacing (6 ft). Don't mix them up.
210.19(A)Continuous Load Sizing
Conductors for continuous loads must be sized at 125% of the continuous load. Conductor ampacity >= 1.25 x continuous load + 1.00 x non-continuous loadTRAP: The 125% applies to conductor sizing AND OCPD sizing (unless 100%-rated device).
Load Calculations (Art. 220)
220.12General Lighting Load
Dwellings: 3 VA/sq ft. Each small appliance/laundry circuit: 1,500 VA. Lighting load = square footage x 3 VA + (# SA circuits x 1,500) + (1 laundry x 1,500)
Demand factors (Table 220.42): First 3,000 VA at 100%, remainder at 35%.
Table 220.55Range Demand Loads
Single range (8.75-12 kW): demand = 8 kW. Do NOT use nameplate rating. For multiple ranges, use table column C values directly. 1 range (<=12 kW) = 8 kW demand | 3 ranges (<=12 kW) = 14 kW demandTRAP: Using the actual 12 kW nameplate instead of the 8 kW table demand is the #1 calculation error.
220.61Neutral Load Calculation
240V range neutral: 70% of the demand load from Table 220.55. Range neutral = demand load x 0.70TRAP: The 70% factor applies to the TABLE demand (8 kW), not the nameplate rating.
Grounding & Bonding (Art. 250)
250.24 / 250.28Main Bonding Jumper
The MBJ connects grounded conductor (neutral) to EGC at the service. This is the only place neutral and ground are bonded. Never re-bond in a sub-panel. TRAP: Bonding neutral to ground in a sub-panel creates parallel paths and is a code violation.
250.50-250.56Grounding Electrodes
All present electrodes must be bonded together. Ufer ground: 20 ft of #4 AWG bare copper in concrete. Ground rod: if one rod exceeds 25 ohms, add a second at least 6 ft away. Two rods = no further testing required. TRAP: Two rods satisfy the requirement regardless of final resistance. No third rod needed.
Table 250.66GEC Sizing
GEC size is based on service conductor size. Common break points: 2 AWG Cu service = 8 AWG Cu GEC 1/0 AWG Cu service = 6 AWG Cu GEC 2/0 AWG Cu service = 4 AWG Cu GEC TRAP: GEC is sized from Table 250.66, NOT from the ampacity table. Different tables.
Table 250.122EGC Sizing
EGC size is based on the OCPD rating, not conductor ampacity. 20A OCPD = 12 AWG Cu EGC | 60A = 10 AWG | 100A = 8 AWG | 200A = 6 AWG TRAP: EGC table (250.122) uses OCPD size. GEC table (250.66) uses conductor size. Don't confuse them.
Overcurrent Protection (Art. 240)
240.4(D)Small Conductor Protection
Hard limits for small copper conductors: 14 AWG = 15A max OCPD | 12 AWG = 20A max | 10 AWG = 30A max TRAP: A 20A breaker on 14 AWG wire is ALWAYS a violation, regardless of calculated load.
240.21(B)Tap Rules
10-foot tap: length <= 10 ft, ampacity >= calculated load, terminates in single OCPD, enclosed in raceway. 25-foot tap: length <= 25 ft, ampacity >= 1/3 of feeder OCPD, terminates in single OCPD, protected from damage. 25-ft tap minimum ampacity = feeder OCPD rating / 3TRAP: The 1/3 rule applies to 25-ft taps only. 10-ft taps must carry the full calculated load.
Conductors & Raceways (Art. 310, 300)
Table 310.16Conductor Ampacity
The most-referenced table in the NEC. Common values (75C column, copper): 14 AWG = 20A | 12 AWG = 25A | 10 AWG = 35A | 8 AWG = 50A | 6 AWG = 65A 4 AWG = 85A | 3 AWG = 100A | 2 AWG = 115A | 1/0 = 150A | 2/0 = 175A TRAP: These are 75C values. Terminal ratings (240.4(D)) still cap 14 AWG at 15A and 12 AWG at 20A.
310.15(C)(1)Conduit Fill Derating
More than 3 current-carrying conductors in a raceway requires ampacity adjustment: 4-6 conductors = 80% | 7-9 = 70% | 10-20 = 50% | 21-30 = 45% Adjusted ampacity = Table 310.16 value x derating factorTRAP: Neutrals carrying only unbalanced current are NOT counted. Equipment grounds are NOT counted.
Motors & Special Equipment (Art. 430)
430.52 / 430.6Motor Circuit Sizing
Motor conductor: 125% of motor FLC (from Table 430.248/250, NOT nameplate). Motor OCPD: use Table 430.52 percentages (dual-element fuse: 175% of FLC; inverse-time breaker: 250% of FLC). Motor conductor = FLC x 1.25 | Motor breaker = FLC x 2.50 (round UP to standard size)TRAP: ALWAYS use table FLC values, NEVER nameplate amps, for motor circuit calculations.
Go Deeper
NEC Cram Sheet Pro
Liked this? The Pro version has full ampacity tables (310.16), box fill calcs, conduit fill, voltage drop formulas, dwelling unit load calc worksheet, motor sizing, and every formula you need — all printable.
One-time: $9.99
Study Smarter
Want an AI tutor that explains all of this?
CertifyPro covers all 20 of these NEC articles and more. 225+ practice questions, 18 modules, a full sim exam, and an AI tutor that breaks down every answer in plain English.